UPDATE-- Rumbrook-Knollwood Water Transmission Main Progress Report I thought I'd write to residents impacted by the important Rumbrook-Knollwood transmission main infrastructure project. I understand that residents along the route have been inconvenienced by the project. We want to thank you for your cooperation. This is an extremely important project. If we don't connect the two facilities and if there is a malfunction residents could have no water. Think: Con Ed power outages. By connecting Rumbrook with Knollwood your water supply is something you can always count on. The following info might be of interest to you. Construction work for the 30-inch transmission main began the first week of May. Nearly 4,000 feet of pipe is installed Work is on-going for control vaults at Knollwood Road near Stadium Road Work is on-going along Canterbury Road and will soon be on West Hartsdale toward Old Knollwood Road. More details on the town website